Microsoft Project scheduling services for government and commercial contractors

Microsoft Project CPM schedules that meet owner and agency specs, with clean logic, resource loading and monthly updates.

✓ Flat-fee quote within 24 hours

✓ Experienced CPM schedulers

✓ Baselines, updates and P6 conversions

Prefer to talk first? Call (833) 777-6276

Get a flat-fee quote in 24 hours

Tell us about your project. You get a flat-fee quote within 24 hours. NDA on request.

    or email your files to info@consultleopard.com

    Trusted by general contractors on federal, data center and commercial projects

    Royce Construction Services logoHunt Builders Corporation logoKellogg and Kimsey logoChugach Government Solutions logoDonlar Construction logoCrossland Construction logo
    • 10

      monthly Microsoft Project updates, each with a narrative and cost report

      Hines VA Hospital, IL · Blue Yonder

    • 3 events

      in one time impact analysis, alongside 6 monthly Microsoft Project updates

      Lovell Federal Health Care Center wayfinding, IL · Blue Yonder

    • Monthly

      Microsoft Project updates for the owner, aligned with the P6 schedule we maintain

      DartPoints CVG data center, OH · Hunt Builders

    Already have a schedule? Send the XER or MPP for a free DCMA 14-point schedule check: a written narrative with recommendations in 2–3 days, depending on project size.

    Approvedby the VA contracting officer’s representative

    Recent result

    Surgical HVAC replacement, Lovell Federal Health Care Center, North Chicago, IL

    Microsoft Project baseline phased around four operating rooms, with a night-shift calendar for occupied areas.

    Client: Blue Yonder

    You are under pressure to deliver and the schedule cannot be an afterthought

    Commercial and public projects are won and lost by how well you manage time. For many general contractors, Microsoft Project is required by the owner, the agency, or the design build partner. You did not enter construction to wrestle with logic ties and resource dependencies.

    A baseline, a monthly update or a recovery schedule after a delay: each one has to be accurate and defensible. That is where we step in.

    When the schedule fails the project struggles

    Delays with No Clear Cause

    When dependencies and logic are not tied well, it is hard to show who or what caused a delay. Recovery becomes guesswork.

    Missed milestones and rejections

    Your update was on time. The logic did not make sense. Reviewers sent it back and payment slipped another thirty days.

    Time lost inside Microsoft Project

    Construction teams need a real plan. If your schedule does not reflect jobsite realities, the field loses alignment and control.

    How our Microsoft Project scheduling process works

    Step 01: Send Your Specs

    Send your specs, milestones or bid documents, or call (833) 777-6276 to talk it through.

    Step 02: Flat-Fee Quote in 24 Hours

    Get a flat-fee quote within 24 hours, based on scope and urgency.

    Step 03: Approved Schedule

    Get your approved schedule. Draft baselines typically arrive within 7 days, with unlimited revisions until approved. We stay on for updates and owner coordination.

    What you get with every Microsoft Project schedule

    Clear deliverables in the formats your owner and reviewer ask for, on every baseline and every update. Owners can also hire us for owner-side schedule review.

    Baseline Package

    A logic-driven Microsoft Project baseline (MPP) with WBS, calendars, resources and costs, plus a PDF Gantt chart and basis-of-schedule narrative.

    Monthly Update Package

    A progressed MPP update with a written narrative and a critical path and float report, ready for your owner’s review and your pay app.

    Spec-Compliant Submittals

    Formatted to your owner’s or agency’s specification, with reviewer comments answered and unlimited revisions until approved.

    P6 Conversion and Delay Support

    XER-to-MPP and MPP-to-XER conversions with the logic intact, plus time impact analysis and recovery schedules when the job slips.

    Microsoft Project Gantt chart filtered to the critical path, showing a fragnet, MEP rough-in and VA review activities with percent complete
    A Microsoft Project update from one of our projects, filtered to the critical path, with the fragnet shown at the top.

    Microsoft Project results for contractors

    DartPoints CVG Data Center, Cincinnati, OH

    Hunt Builders

    Monthly Microsoft Project updates for the owner, aligned with the Level 3 and Level 5 Primavera P6 baseline program we built and update weekly.

    VA Administration Building, Gainesville, FL

    V-Line Services

    Rejected Microsoft Project updates were rebuilt in Primavera P6. We delivered 14 monthly updates, and the March 2024 update forecast completion ahead of the approved date.

    Residence Inn, Ormond Beach, FL

    Kellogg & Kimsey

    Our time impact analysis supported a 59-day TCO extension, and it was granted.

    “Leopard Project Controls brought clarity and speed to our Microsoft Project schedule process. The team understood our specs, created a defensible baseline quickly, and helped us move through review without delay. Communication was excellent and the results were even better.”

    Frank Edwards, Project Manager

    Hunt Builders / Data Center Construction Project

    Microsoft Project schedules on recent projects

    Surgical HVAC Systems Replacement, Lovell Federal Health Care Center

    Client: Blue Yonder Inc.

    North Chicago, IL
    Microsoft Project baseline, approved by the VA contracting officer’s representative

    Replace Air Handling Unit, Building 45

    Client: Blue Yonder Inc.

    Hines VA Hospital, IL
    10 monthly Microsoft Project updates with a narrative and cost report

    Facility Wayfinding, Lovell Federal Health Care Center

    Client: Blue Yonder Inc.

    North Chicago, IL
    6 monthly Microsoft Project updates and a time impact analysis of three delay events

    DartPoints CVG Data Center Expansion

    Client: Hunt Builders

    Cincinnati, OH
    Monthly Microsoft Project updates for the owner, aligned with the P6 schedule

    A scheduling team that knows the field and the software

    You run crews, RFIs and owner meetings. You shouldn’t also have to untangle Microsoft Project logic the night before an update is due. We take the schedule off your plate and keep it in step with how the job is really being built.

    Our schedulers build and update Microsoft Project and Primavera P6 schedules for federal contractors, data centers and commercial GCs. You get a flat-fee quote in 24 hours and revisions until the schedule is approved.

    Get My Flat-Fee Quote

    Microsoft Project scheduling consultants for commercial and government projects

    Leopard Project Controls provides Microsoft Project scheduling services to general contractors whose owner, agency or design-build partner requires an MPP schedule. Our schedulers build the baseline schedule, run the monthly schedule updates and deliver the narrative, PDF Gantt and native file your reviewer asks for. You get a Microsoft Project schedule consultant team that knows construction as well as the software.

    A Microsoft Project schedule only holds up in review when the logic does. We tie every activity, keep constraints and leads to a minimum, set calendars to the contract and show a clear critical path, so the reviewer sees a real plan. We also handle resource loading and cost loading to your schedule of values, so progress and pay apps line up.

    Many owners work in Microsoft Project while the contractor’s team keeps the schedule in Primavera P6. We build and maintain both schedule files and keep them in sync every update. On the DartPoints CVG data center in Cincinnati, we give the owner monthly Microsoft Project updates aligned with the P6 program we built for Hunt Builders. When the job slips, we prepare time impact analysis and recovery schedules that document the delay.

    Choosing a Microsoft Project scheduling company comes down to approvals, turnaround and price. We send a flat-fee quote within 24 hours, draft baselines typically arrive within 7 days, and we revise until the schedule is approved. If your owner requires Primavera, see our Primavera P6 scheduling services; for software-neutral support, see our CPM scheduling services.

    Frequently asked questions

    Some contracts require it, especially for public sector work and design build delivery. Even when it is not required, Microsoft Project is widely accepted for planning and progress reporting.

    Yes. We can audit, clean up, and rebuild existing Microsoft Project files. We can also import spreadsheets to produce a logic driven CPM schedule.

    Yes. NDA on request. We honor every confidentiality term we sign and never name a client or project on our website without permission.

    Draft baselines typically arrive within 7 days. We then revise the schedule, without limit, until it is approved.

    Yes. When the owner works in Microsoft Project and your team keeps the schedule in Primavera P6, we build and maintain both schedule files and align them every update, so the owner’s MPP schedule and your P6 schedule show the same logic, dates and critical path.

    We provide clear flat-fee pricing based on scope, urgency, and duration. You get a flat-fee quote within 24 hours.

    Your next step

    Ready to get your Microsoft Project schedule approved?

    Send your specs or book a quick discovery call. Our consultants will take it from there and help you submit with confidence.

    1. Send your spec and filesThe scheduling spec section, contract dates and any XER or MPP file you already have.
    2. Get a flat-fee quote in 24 hoursOne fixed price, the deliverables and the delivery date in writing.
    3. Revise until approvedWe build it to the spec and make unlimited revisions until it is approved.

    Why contractors call us

    • Primavera P6 and MS Project schedules built to USACE, NAVFAC, VA and DOT specs
    • Draft baselines typically within 7 days
    • Monthly update and narrative within 1–2 working days of your progress data
    • One flat fee per update, or one flat monthly fee for the whole project
    • NDA on request

    Not sure your current schedule will pass? Get a free DCMA 14-point schedule check. Prefer email? info@consultleopard.com

    Start your CPM scheduling request

    Upload your specs and get a Primavera P6 or MS Project baseline built to your contract, with a flat-fee quote in 24 hours and unlimited revisions until approved.

      Call (833) 777-6276Get My Quote