LEOPARD PROJECT CONTROLS

Recovery Vs Revised P6 Schedule

Comparison Between Project Recovery and Revised P6 Schedule

In this article, we aim to explore the importance of project recovery schedules and their differences from revised P6 schedules. At the start of any project, a pre-approved P6 schedule is developed to highlight the planned sequences for the project. According to PMI, they define the baseline schedule as the authorized version of the scheduled model that executives use as a comparison benchmark with actual outcomes.
Recovery or revised schedules are employed when there is a modification in planned values within the baseline schedule. These changes could be due to circumstantial events or delays caused by all parties involved. A recovery schedule in P6 outlines strategic plans and measures intended by project teams to get projects on track.

Whereas a revised schedule in P6 comes into play when alterations arise concerning project scope, rescheduling, and resource requirements. We can conclude that the primary distinction between recovery and revised schedules lies within completion dates; where recovery schedules have equal completion dates compared to original “baseline completion dates,” while revised ones entail changes made towards initial completion dates.

It is an entirely new plan reflecting modifications implemented within projects. Below are steps to create a revised schedule using P6.

Recovery Vs Revised P6 Schedule

Find the changes that need to be made to the project schedule.

  1. Update the project schedule to reflect the changes.
  2. Analyze the new critical path and adjust the schedule as needed.

 

Uses for recovery or revised schedule

  1. Recovery schedule:
  • Construction acceleration
  • The not realistic original schedule
  • Changes in resources
  1. Revised schedule:
  • Delayed project
  • Delays in the critical path
  • Delays in the project
  • Variations or changes in project scope

Impact analysis

Impact analysis plays a significant role in implementing revised or recovery schedules.

1- Revised schedule impact analysis: it assesses the impact of schedule changes, where changes have various aspects as:

  • Project timeline.
  • Resources
  • Cost
  • Risks

2- Recovery schedule impact analysis: it focuses on assessing the delay events and changes in schedule consequences.

  • Time-sensitive activities.
  • Resource requirements
  • Project dependencies
  • Stakeholder expectations

Impact analysis is tied to the implementation of revised and recovery schedules. It helps project controls to check the consequences of schedule changes on all the project elements. To learn more about the different EOT Analyses, you can check our article: EOT (Extension of Time)

Implementation and execution

When we have a delay and request to send a recovery/ revised schedule, the below steps will discuss the best way to prepare this schedule:

1- Remove the baseline if any is assigned.

Recovery Vs Revised P6 Schedule

Recovery Vs Revised P6 Schedule

2- Insert any added scope of work.

3- Fix out-of-sequence activities.

Firstly, view the log and fix all the out-of-sequence activities to zero.

4- Fix unsatisfied relationships.

5- Fix finished dates to existing dates or new approved dates.

  • Assign “Must Finish By” date.

  • Then apply the longest path filter.6- Remaining early start date = data date +1

7- Add or fix cost loading.

8- Fix the remaining duration decimal.

9- Fix actual start dates of in progress.

  • Change the actual duration that has higher values to be equal to the old actual duration

By using Excel, you can export data and then import it again to Primavera.

Recovery Vs Revised P6 Schedule

10- Global Change for completed and in progress.

  • Global change #1:
    1. Activity Status =Completed
    2. Original Duration = At completion

  • Global Change #2:
    1. Activity Status =Completed
    2. Planned Start = Actual Start
    3. Planned Finish = Actual Finish

  • Global Change #3:
    1. Activity Status =In Progress
    2. Planned Start = Actual Start

Contact Leopard Project Controls for your next Construction Schedule Project.

Share This Blog, Choose Your Platform!

Go to Top