An Introduction to LNG Tanks and Construction Sequence

Liquified Natural Gas (LNG) is emerging as an important component of the global energy landscape, offering a cleaner and energy-efficient alternative to traditional fossil fuels. Delve into the significance of LNG Tanks and the Construction Sequence, exploring the key elements shaping this transformative energy landscape.

LNG tanks or Liquefied Natural Gas tanks are specialized storage tanks that are designed to store natural gas in its liquid form. These tanks can be found in the ground, above ground, or in LNG carriers.

The most important characteristic of LNG tanks is the ability to store LNG at very low temperatures of -162 degrees Celsius (-260 degrees Fahrenheit) through a process called liquefaction. At these temperatures, natural gas changes from a gaseous state to a liquid state, becoming significantly denser and easier to transport and store.

LNG tanks are used for various purposes:

1. Storage: LNG tanks are being utilized at production facilities and storage terminals to store large quantities of liquified natural gas. Tanks vary in size and capacity depending on the requirement.

2. Transportation: LNG is often transported to long distances over sea, rail, or road. The specially designed LNG carriers transport the liquid from exporting terminals to importing terminals.

3. Distribution: In some cases, LNG is transported to distribution points via trucks or railcars to consumers who are not connected to natural gas pipelines. These careers are insulated and designed to maintain the low temperatures of LNG during transit.

4. LNG as Fuel: LNG is a clean burning fuel and hence is used for various applications including trucks, buses, ships, and some power plants.

Leopard Projects Control provides expert guidance and strategic oversight to optimize the construction schedule for LNG tank projects, ensuring timely and efficient project completion.

Typical Work Breakdown Structure in any LNG Tank Construction

A typical WBS followed in any LNG tank construction is outlined below:

Early construction work

Soil investigation

Site office and temporary facilities

Batching plant

Fabrications at site

Fabrication of anchor plates

Corner liner anchor

Secondary barrier shell top anchor

Side liner anchor (lower)

Side liner anchor (upper)

Fabrication of liner plates

Bottom liner plate

Side liner plate (lower)

Side liner plate (upper)

Fabrication of roof

Roof Skelton

Roof plate

Roof ring plate

Fabrication of suspension deck

Suspended deck beam

Suspended deck plate

Suspension rod

Fabrication of inner tank

Inner tank annular plate

Inner tank shell stiffener

Inner tank shell plate

Inner tank bottom plate

Fabrication of secondary barrier

Secondary barrier annular plate

Secondary barrier shell plate

Secondary barrier bottom plate

Fabrication of nozzles

Manholes

Nozzles

Fabrication of structural steel works

Structural steel works – mild steel

Structural steel works – ss

Construction for tank

Civil works

Piling

Pile Built-up

Pile Built-up

Base slab

Wall

Roof

Post-tensioning

Structural steelwork

Erection of structural steel

Mechanical works

Erection of anchor plates

Erection of liner plates

Pre-assembly of roof skeleton

Erection of roof blocks

Erection of suspension deck

Erection of inner tank (9%)

Erection of secondary barriers

Erection of manhole/nozzle

Insulation works

Hydro test

Machinery works

Piping works

Inner piping

Outer piping

Electrical works

Power & control cable

Cable tray & conduit

Grounding & lightning

Cathodic protection

Instrumentation works

Cable tray

Cabling

Loop testing

Pre-commissioning

Drying & N2 purge

Commissioning assistance

Brief Construction sequence of LNG tanks

Site selection and preparation:

The site of construction is to be chosen based on factors like proximity to LNG sources or consumption centers and local regulations.

Site preparation includes all sorts of early civil works including grading, soil stabilization, etc.

Foundation construction:

The foundation consists of reinforced concrete footings (mostly, bored cast-in-situ pile foundation), followed by a base slab engineered to distribute the immense weight evenly.

Piles installation nearing completion

2. Piles installation nearing completion

The base slab construction shall be completed by segregating the slab into various segments

Shuttering for bases lab in progress

3. Shuttering for baseslab in progress

Concreting in progress for baseslab

4. Concreting in progress for baseslab

Fabrication works:

As a part of the mechanical works, the fabrication of the various liner plates and other structural steel works are initiated.

Rafter Fabrication

5. Rafter fabrication

Corner liner fabrication

6. Corner liner fabrication

Tank bottom and shell assembly:

The corner ring is constructed before the base slab concreting and wall construction. This ensures the effective development of pre-stress between the wall and bottom slab. After the corner ring is cured, prestressing (PS) of the bottom slab and half of the wall is performed using tendons.

The tank’s bottom and shell, which are made of high-grade steel are added onto the tank bottom and wall liners.

This activity would require precision welding to ensure the tank’s structural integrity and QA/QC measures are in place.

Typical sequence of construction

7. Typical sequence of construction – Foundation, wall, ring beam, and suspended deck

Be sure to read our informative article on the impactful use of artificial intelligence and machine learning in construction projects.

Wall construction:

The exterior wall of the tank is RCC (reinforced cement concrete) and the concreting of the same shall be with the help of a climbing formwork.

Climbing formwork

8. Climbing formwork

The PS tendons in the ring beam are installed in two steps. The initial half of PS tendon installation takes place before roof construction and installation of the latter part takes place after concrete roof construction.

Climbing Formwork

9. Climbing Formwork

Insulation installation:

To maintain the extremely low temperatures of LNG, insulation is provided to maintain the cryogenic state.

Materials such as perlite or foam glass are applied to the tank’s inner surface.

Roof installation:

The tank’s roof and the suspended deck are installed within the outer tank after the wall construction is complete. The roof is raised to the designated position through a process called Air Raising by using air pressure that is created by several blowers.

Once the air-raising activity is completed, the dome roof is temporarily welded at the top of the RCC wall.

Inner view of tank

10. Inner view of tank – Rafter installation

Top view of Rafters

10. Top view of Rafters

After Roof Airlifting

12. After Roof Airlifting

Concrete is placed above the steel roof.

Roof Concreting

Inner tank:

The inner tank is installed after the roof concrete is completed.

Welding of Inner tank plate

The material used for inner tank linings is 9% Nickel, as they can remain ductile and crack-resistant when exposed to extremely low temperatures.

Testing & commissioning:

Rigorous testing, including pressure and hydro tests, is conducted to verify the tank’s integrity and safety.

Commencement of operations:

Once the local regulatory and other approvals are obtained, the LNG tank is ready for service. It plays an important role in the LNG supply chain, aiding the storage and distribution of LNG to meet energy demands.

Conclusion:

LNG tanks are essential components in today’s energy industry and enable safe and efficient storage of natural gas. The process of construction, fabrication, and welding involves precision, adherence to safety standards, and rigorous quality control.