How To Import Budgeted Total Cost From Excel File To Primavera P6

The Cost loading for Primavera P6 Schedule requires Budgeted Total Cost for the activities as per the Bill of Quantities. Generally, the Budgeted Total Cost is entered manually for the activities in the Primavera P6 schedule. Instead of manually entering the Budgeted Total Cost for each activity, the values shall be imported from the Excel file to the Primavera P6 schedule. To do this we need to follow the steps as follows.

Step 01:

We need to create a new “Resource” for “Budgeted Total Cost” in the Primavera P6 schedule to transfer the values from the Excel file to the resource. To do this we will click “Enterprises” and “Resources.” In the “Resources” window, we will click “Add,” enter “Resource ID,” and “Resource Name,” as “BOQ,” and “Cost,” respectively, and click “Next.” In the “Resource Type” window, we will select “Nonlabor” as “Resource Type,” and click “Finish.”

Add New Resource

Figure 1: Add new “Resource”

Add Resource ID

Figure 2: Add “Resource ID,” and “Resource Name” for new Resource

Select Resource Type

Figure 3: Select “Resource Type.”

Step 02:

We need to export the Primavera P6 Schedule to Spreadsheet (XLSX) format, with the column for the Budgeted Total Cost. To do this we will click “File” and click “Export” to open the “Export Format” window. In the “Export Format” window we will select “Spreadsheet-(XLSX)” and click “Next.” In “Project Type” we will select “Activities,” “Resources,” and “Resource Assignments” and click “Next.” Then in the “Projects to Export” window, we will select the current project and click “Next.”

Export Primavera P6 Schedule to Excel

Figure 4: Export Primavera P6 Schedule to “Excel.”

Select Export Type

Figure 5: Select “Export Type.”

Select Project to Export

Figure 6: Select “Project to Export”

Step 03:

We need to create a new template to export the required data to an Excel file. To do this we will click “Add” in the “Select Template” window. In the “Modify Template” window we will type “Cost” as “Template Name,” and select “Resource Assignments” as “Subject Area.”

Add New Template

Figure 7: “Add New Template”

In the “Modify Template” window we will select “Budgeted Total Cost” from the “Available Options,” click the “Add to list” arrow, and click “OK” to move it to the “Selected Options,” In the “Select Template” window we will select the aforesaid new template and click “Next.” Then in the “SELECT XLSX File” window we will select the path to save the Excel file, and click “Next.” When the “Summary” window appears, we will click “Finish.”

Modify Template

Figure 8: “Modify Template”

Select XLSX File

Figure 9: “Select XLSX File”

Excel Export Summary

Figure 10: “Excel Export Summary”

Step 04:

We will click “Columns”, in the “Columns” window, select “Budgeted Total Cost” from “Cost” in “Available Options” and move it to “Selected Option,” We will save the Layout as “BOQ Cost.” Note that the “Budgeted Total Cost “will be displayed as $0, before importing the values from the Excel file as shown in the figure 12 below.

Adding Column for Budgeted Total Cost

Figure 11: Adding Column for “Budgeted Total Cost”

Budgeted Total Cost

Figure 12: “Budgeted Total Cost” in Primavera P6 Schedule before importing the values.

We will prepare BOQ (Bill of Quantities) in Excel as per the activities in the Primavera P6 schedule. Then we will open the exported Excel file from Primavera P6 and add a new sheet named “BOQ.” We will copy the Activity ID, Activity Name and Budgeted Total Cost from the BOQ prepared in the Excel file and paste the values in the new sheet named “BOQ” in the exported Excel file.

Adding BOQ

Figure 13: Adding BOQ as a new sheet in exported Excel file.

Then we will transfer the values of “Budgeted Total Cost” from column number 3 of the “BOQ” sheet to column number 9 of the “TASKRSRC” sheet of exported Excel file using the “VLOOKUP” formula. Then we will drag the formula to all the rows in column number 9 of the “TASKRSRC” sheet.

Transfer the values for Budgeted Total Cost

Figure 14: Transfer the values for “Budgeted Total Cost” to the “TASKRSRC” sheet.

Step 05:

To import the Excel file with values of “Budgeted Total Cost” to Primavera P6 schedule, we will click “File,” “Import,” select “Spreadsheet (XLSX)” as “Import Format” and click “Next.” In the “Import Type” window we will select “Project” and click “Next.” Then we will select the exported Excel file saved with values of “Budgeted Total Cost” and click “Next.”

Select Import Format

Figure 15: Select “Import Format”

Select Excel File

Figure 16: “Select Excel File”

Once, we select the Excel file and click “Next,” the schedule navigates to a new window “Import Type,” wherein we will select “Activities,” “Resources,” “Resource Assignments,” and click “Next.”

Select Import Type

Figure 17: Select “Import Type”

In the Next window “Import Project Options” we will select the Primavera P6 schedule which is open in the “Import To” column and click “Next.” The Primavera P6 navigates to the next window “Summary” and we will click “Finish.”

Import Project Options

Figure 18: “Import Project Options”

Excel Import Summary

Figure 19: “Excel Import Summary”

Import Result

Figure 20: “Import Result”

After the import process, we will open the Primavera P6 Schedule with a layout saved as “BOQ Cost.” The “Budgeted Total Cost” values are now available in the schedule for the respective activities as shown in the figure below.

Budgeted Total Cost

Figure 21: “Budgeted Total Cost” after importing the values from the Excel file.

Conclusion:

This process of importing Budgeted Total Cost from an Excel file is a useful technique requiring less time than manually entering the values for each activity in the Primavera P6 schedule.