Primavera P6 Activity Steps
Setting a Baseline in Primavera P6
Baselines let you track plan vs. actual for a project plan. This gives you an understanding of where your project is currently, compared to where it was when it first started, or perhaps at some other phase gate or key milestone. Project Baseline The project baseline in Primavera P6 is the official baseline for your project. It is usually something that is established at the very beginning of your project so that you can compare it to the current state of your project in the future. How to maintain and assign your baseline? After creating your baseline, go to Project [...]
HOW TO USE THE ACTIVITY STEPS FEATURE IN PRIMAVERA P6
In Primavera P6, we can break down an activity into smaller unit works by using the “Activity Step” feature. This feature can be used to assign a lot of “steps” within the same activity instead of creating many additional activities in the program. The “steps” can be used to calculate the Activity % Complete for an activity based on the individual weighted value assigned for each step. The procedures to add “Activity Steps” for activity and use them to update the progress are as below: Customize Activity Details to add the Steps Tab To add Steps in “Activity Details” [...]