P6 Activity Steps Feature
HOW TO USE THE ACTIVITY STEPS FEATURE IN PRIMAVERA P6
In Primavera P6, we can break down an activity into smaller unit works by using the “Activity Step” feature. This feature can be used to assign a lot of “steps” within the same activity instead of creating many additional activities in the program. The “steps” can be used to calculate the Activity % Complete for an activity based on the individual weighted value assigned for each step. The procedures to add “Activity Steps” for activity and use them to update the progress are as below: Customize Activity Details to add the Steps Tab To add Steps in “Activity Details” [...]