Calendars in Primavera P6
Calendars in Primavera P6
There are three types of calendars in Primavera P6. Before you assign a calendar to your project, you first have to determine which type of calendar it needs. Global – this calendar can be used for all projects and resources under the organization’s projects. The calendar has a 5-day workweek, 8-hour day, non-working days, and holidays from the organization’s calendar. Project – this calendar is project specific, meaning it is set for the project which you are working on. Resource – this calendar can be assigned to the resources only but not for the activities that are under the project. [...]