How to remove progress from a Primavera P6 Schedule

The following instruction shows how to deprogress a schedule and reuse the schedule for other same projects:

Step 1:

Add the following columns: Actual Labor Units, Actual Non-labor Units, Budgeted Nonlabor Units, Budgeted Labor Units, Activity Status

Primavera P6 budgeted and actual

Step 2:

On the calculations tab of the project Window, select “Link Budget and At Completion for not started activities”, also select the option “Reset Remaining Duration and Units to Original”.

Primavera P6 Calculations Tab

Step 3:

On the Dates tab of the project, change the project planned start date to the new project planned start date.

Primavera P6 Project Date Tab

Step 4:

Schedule the project with the Data Date as the Planned Start Date of the New Project.

Primavera P6 Scheduling Options

Step 5:

Now we are ready to de-progress the schedule. Using the “Fill Down” tool to set all activities’ actual units to Zero (labor units, non-labor units)

Fill down tool to set activities status to not started

Step 6:

If the project uses resource materials, use Global Change to set actual Material Units to Zero.

Primavera P6 global change to Zero Costs

Step 7:

On the “Activity Status” column, use the “Fill Down” tool to set “Activity Status” to “Not Started”

Fill down tool to set activities status to not started

Step 8: To reset the actual cost to Zero, use global change for “Activity Resource Assignments” and set “Actual Regular Cost” and “Actual Overtime Cost” to Zero.

Primavera P6 global change to Zero Costs

The project Primavera P6 schedule is now de-progressed and ready to be used.