At the end of 2022, Oracle released the highly anticipated version 22.12 of Primavera P6 Professional, further solidifying its position as a leading project management tool. With each update, Primavera P6 consistently demonstrates its commitment to innovation by introducing new features and enhancements that cater to the evolving needs of project managers. The latest release, Primavera P6 22.12, is no exception, offering a range of powerful capabilities that enhance the viewing and management of project schedules.
With its reputation as a leading project management solution in the industry, Oracle Primavera P6 22.12 continues to set the bar high for efficient project planning and execution. In this article, we will delve into the exciting new features and enhancements introduced in Primavera P6 22.12, and explore how they further elevate the software’s capabilities to drive successful project outcomes.
Enhancements to Viewing and Analyzing Project Data
Effective analysis and tracking of project performance are crucial for CPM schedulers. To facilitate this process, Primavera P6 Professional 22.12 has introduced several new features to enhance the viewing and analysis of project data.
View Projects Side-by-Side with Additional Activities Page:
One of the significant changes in this release is the ability to view projects side-by-side. By selecting the “Additional Activities View” option under the Projects menu, a second Activities screen opens, which can be placed alongside the original Activities screen.
Both screens display data for all open projects, and you can use different layouts to customize the displayed project data.
This feature enables users to compare and analyze different views of the same project simultaneously. Additionally, activities can be copied and pasted or dragged and dropped between screens, streamlining the process of adjusting activity data.
Perform Quantitative Analysis using Check Schedule Report:
Another useful addition is the Check Schedule Report tool, available under the Tools menu.
This tool enables quantitative analysis of open projects by evaluating various schedule analysis metrics, such as those outlined in the DCMA 14 Point Assessment. Users can select specific metrics to analyze and define target percentages for each metric.
The report provides a score for each metric and highlights activities that meet the target metrics, helping users identify and address any schedule issues.
Specify Timeframes for Finish Date Filters:
Primavera P6 22.12 introduces the ability to specify timeframes for Finish Date fields in filters. Previously, filters with Finish Date fields selected the end of the time frame by default. With this update, users can now define whether to use the start or end of the timeframe for Finish Date filters.
This option can be configured in the Admin Preferences under the General tab, providing greater flexibility in filtering project data based on specific timeframes.
Arrange Order of Sort Fields:
In this version, P6 Professional allows users to rearrange the order of Sort fields. When creating a Sort order in the Group and Sort window, users can move sort columns up or down to adjust the primary Sort order as needed.
This feature simplifies the process of customizing the sorting of activities based on specific criteria, enhancing the overall project data organization.
Enhancements to Adjusting Project Data
Primavera P6 22.12 introduces several enhancements to the adjustment of project data, making it easier to add and organize data within the schedule.
Copy and Paste a Range of Cells for Resource Usage:
Users can now copy and paste values from a range of cells in the Resource Usage Spreadsheet and the Resource Assignments page. This functionality allows for more efficient tracking of planned and actual units and costs for assigned resources. It also supports assigning units and costs using future bucket planning. By selecting a range of cells, right-clicking, and choosing the Copy Range option or using the keyboard shortcut Shift+Ctrl+C, users can copy multiple cells within a spreadsheet row.
Similarly, pasting the copied values will place them within the selected row. Only the values within the cells are copied and pasted, allowing for seamless transfer of data between cells with different units of measure.
Additional Columns for Assigning Baselines:
The Assign Baselines window now includes additional columns to aid in the selection of appropriate baselines. The new columns provide information such as the Date Added and the Last Update Date for each baseline, allowing users to make more informed decisions when assigning baselines to projects.
This enhancement streamlines the baseline assignment process and provides better visibility into the history and timing of each baseline.
Earned Value Fields available now for Resource Assignments:
Primavera P6 22.12 introduces Earned Value (EV) fields for resource assignments also. These EV fields can be customized to include Assignment % Complete, Budget at Completion, Estimate to Complete, and Earned Value.
The inclusion of EV fields for resource assignments enhances the Earned Value analysis capabilities within Primavera P6. Users can now track and evaluate the performance of resources based on earned value metrics, enabling more accurate cost and schedule forecasting.
Importing and Exporting Enhancements
Efficient data exchange is essential in project management, and Primavera P6 22.12 introduces several enhancements to improve the importing and exporting capabilities of the software.
Exporting Projects in different new formats:
Primavera P6 Professional 22.12 now allows exporting projects as IPMDAR files. This format complies with the US Department of Defense’s Integrated Program Management Data and Analysis Reporting (IPMDAR) format.
More Options when Importing XML Data:
The XML file import options have been expanded in this version, providing users with more control over the data they choose to import. Users can now select specific data elements from XML files, including resource calendars and responsible managers. This granular control enhances the import process by allowing users to import only the necessary information, reducing the risk of data duplication or inconsistencies.
Duplicate Import and Export Templates:
One of the standout features in Primavera P6 Professional 22.12 is the ability to duplicate project templates. This functionality allows project managers to replicate existing templates and make necessary modifications, significantly reducing setup time for similar projects. Through this feature, project managers and schedulers can ensure consistency across projects and expedite the initiation phase.
The ability to duplicate project templates offers immense time savings and efficiency gains. Project managers and schedulers no longer need to recreate templates from scratch for each project. They can simply duplicate an existing template, customize it as per the project requirements, and start the project with a solid foundation. This feature promotes standardization and ensures that best practices are consistently applied across projects.
This feature eliminates the need to manually recreate templates for different file types, improving efficiency and consistency in data exchange processes.
Options for Adjusting OBS Assignments:
When copying projects across EPS (Enterprise Project Structure) layers, Primavera P6 22.12 provides options to adjust Organizational Breakdown Structure (OBS) assignments. OBS assignments determine the responsible managers for projects and activities within the organizational hierarchy.
With this update, users can control OBS assignments when copying projects, ensuring that responsible managers are accurately assigned based on the destination EPS layer.
Conclusion:
Oracle Primavera P6 Professional 22.12 introduces numerous enhancements across different aspects of project management. From improved project data analysis and adjustment capabilities to enhanced import/export options, these updates provide users with greater flexibility, efficiency, and control over their projects. With each release, Oracle continues to refine and expand Primavera P6, making it a powerful tool for project schedulers and managers. These new features contribute to improved project visibility, streamlined workflows, and better decision-making, ultimately leading to successful project outcomes.
With Leopard Project Controls, you can leverage these powerful features and ensure successful project outcomes. Visit our website, Leopard Project Controls, for comprehensive project control services and harness the full potential of Oracle Primavera P6 for your projects.
We at Leopards Project Controls provide fast and high-quality CPM Scheduling services, leveraging 18+ years of experience. As a certified SWaM business, we deliver comprehensive project controls services, exceeding client expectations with our expertise and advanced technology solutions.